Case Studies

Advancing across four continents

SAVRES is working with governments and municipalities across the globe — from tackling Kinshasa's waste crisis to bringing zero-combustion clean energy to Guyana.

$29M+

Projected revenue per facility p.a. (after Year 3)

430

Jobs created per facility

25 yrs

Facility life expectancy

DR Congo — Kinshasa

9,000 tonnes of waste accumulating daily

A city of 14.5 million — Africa's third-largest — with no functioning garbage collection system. SAVRES will work with the Congolese government to address a public health catastrophe and restore Kinshasa.

Kingdom of Saudi Arabia

3 × 25MWh facilities — 15M+ tonnes of MSW per year

Developing and maintaining a stake in a minimum of three W2E facilities within five years, establishing KSA as a leader in the global waste-to-energy market and in the negotiation of waste stream availability, distribution and pricing.

Nigeria

4,500 TPD across two states — 24/7 grid export

Modern recycling facilities and W2E power plants across two states, treating a combined 4,500 tonnes per day. Automated sorting and separation centres where local collectors deliver waste directly — converting city refuse into continuous, 24/7 clean electricity exported to the national grid.

Vietnam — Ho Chi Minh City

2,600 TPD — Vietnam's fastest-growing metropolis

Ho Chi Minh City has mandated that at least 80% of municipal solid waste be diverted to recycling and Waste-to-Energy. A high-capacity 2,600 TPD project answers this strategic priority — replacing unsustainable landfills with long-term, modern waste treatment.

Panama

Waste growing faster than infrastructure capacity

One of Latin America's fastest-growing economies, Panama faces mounting waste management challenges. SAVRES solutions will improve public spaces, environmental health and sustainable development for current and future generations.

Guyana

1,000+ TPD — zero-combustion pyrolytic gasification

A 1,000+ tonne-per-day Waste-to-Energy facility converting municipal waste into continuous 24/7 clean power, green hydrogen and biofuels — replacing hazardous, leaching landfills and creating hundreds of skilled local jobs.

Project Rollout

A structured, stage-by-stage delivery model

Each project follows a proven schedule — from feasibility study and business plan through to a fully operational, self-sustaining facility with a 25-year life expectancy.

Stage 2

Waste Recycling (180,000+ t/yr)

12–18 months

Stage 3

Waste to Energy Facilities

18–24 months

Stage 4

Fully operational & producing energy

Year 3

Recycling Snapshot

  • Total completion12–24 months
  • Business plan3 months
  • Land, permits & zoning6 months
  • Feasibility study3 months
  • Waste supply agreement (20yr)2 months
  • Technology completion9–12 months
  • Site commissioning4–8 weeks
  • Life expectancy25+ years

W2E Facility Snapshot

  • Total completion18–24 months
  • Feasibility study6 months
  • Business plan3 months
  • Technology completion9–12 months
  • Front-end engineering & ESIA6–12 months
  • Detailed engineering & EPC18 months
  • Power Purchase Agreement (20yr)3 months
  • Life expectancy25+ years

Your region could be next

Every project begins with a waste stream assessment. Tell us about yours and we'll show you what it could produce — and what it could be worth.

Start a conversation